Registering Property in India, Ranchi

BUILDING A WAREHOUSE
Data as of: January 2006
City: Ranchi

Registration Requirements:
Procedure 1Obtain land use permission
Time to complete:90 days
Cost to complete:no charge
Comment:
Procedure 2*Obtain soil test
Time to complete:3 days
Cost to complete:INR 5,000
Comment:
Procedure 3Apply for building permit
Time to complete:90 days
Cost to complete:included in next procedure
Comment:
Procedure 4Pay building permit fee and obtain building permit
Time to complete:1 day
Cost to complete:INR 20,000
Comment:
Procedure 5Notify Labor department about commencement of construction work
Time to complete:20 days
Cost to complete:no charge
Comment:
Procedure 6*Receive labor inspection
Time to complete:1 day (included in previous procedure)
Cost to complete:no charge
Comment:
Procedure 7Notify the Ranchi Regional Development Authority about the commencement of earth work for foundation
Time to complete:90 days
Cost to complete:no charge
Comment:
Procedure 8*Receive foundation inspection
Time to complete:1 day (included in previous procedure)
Cost to complete:no charge
Comment:
Procedure 9*Notify the Ranchi Regional Development Authority about the start of laying the roof and basement floor level
Time to complete:88 days
Cost to complete:no charge
Comment:
Procedure 10*Receive roof inspection
Time to complete:1 day (included in previous procedure)
Cost to complete:no charge
Comment:
Procedure 11*Notify the Ranchi Regional Development Authority about the completion of finishing work
Time to complete:86 days
Cost to complete:no charge
Comment:
Procedure 12*Receive finishing work inspection
Time to complete:1 day (included in previous procedure)
Cost to complete:no charge
Comment:
Procedure 13Obtain water and sewage connection
Time to complete:15 days
Cost to complete:INR 7,500
Comment:
Procedure 14Obtain no objection certificate from Fire Department
Time to complete:10 days
Cost to complete:INR 250
Comment:
Procedure 15*Receive fire inspection
Time to complete:1 day (included in previous procedure)
Cost to complete:no charge
Comment:
Procedure 16*Apply for the use uplift of underground water from Jharkhand Pollution Control Board
Time to complete:15 days
Cost to complete:no charge
Comment:
Procedure 17*Obtain no objection certificate from Public Health Department
Time to complete:10 days
Cost to complete:no charge
Comment:
Procedure 18*Receive public health inspection
Time to complete:1 day (included in previous procedure)
Cost to complete:no charge
Comment:
Procedure 19*Obtain power connection
Time to complete:180 days
Cost to complete:INR 75,000
Comment:
Procedure 20*Receive electrical inspection
Time to complete:1 day (included in previous procedure)
Cost to complete:no charge
Comment:
Procedure 21*Obtain phone connection
Time to complete:15 days
Cost to complete:INR 2,500
Comment:
Procedure 22Obtain completion certificate
Time to complete:40 days
Cost to complete:INR 2,500
Comment:
Procedure 23*Receive final inspection
Time to complete:1 day (included in previous procedure)
Cost to complete:no charge
Comment:
Procedure 24Apply for occupancy certificate
Time to complete:30 days
Cost to complete:no charge
Comment:
Procedure 25*Receive final inspection
Time to complete:1 day (included in previous procedure)
Cost to complete:no charge
Comment: