Registering Property in India, Jaipur
BUILDING A WAREHOUSEData as of: January 2006
City: Jaipur
Registration Requirements:
| Procedure 1 | Obtain land use permission from Jaipur development authority |
| Time to complete: | 50 days |
| Cost to complete: | INR 8000 |
| Comment: | |
| Procedure 2 | Apply for building permit and pay initial fee |
| Time to complete: | 5 days |
| Cost to complete: | INR 300 |
| Comment: | The company must submit the application to Jaipur Municipal Corporation along with the following documents: a) Five copies (two cloth mounted) of building plan; b) Evidence like Record of Rights (ROR) or a civil court decree as regards title and possessio |
| Procedure 3 | Obtain approval of plans (building permit) and pay final fees |
| Time to complete: | 30 days |
| Cost to complete: | INR 26000 |
| Comment: | Application will be scrutinized. If the application is fit to be approved, a demand will be sent to you by the local authority for payment of license fee and development charges if any. The rate will depend on the proposed uses and the floor area. |
| Procedure 4 | Notify the Municipal Corporation of Jaipur before start of foundation concreting |
| Time to complete: | 35 days |
| Cost to complete: | no charge |
| Comment: | |
| Procedure 5* | Receive inspection from Municipal Corporation of Jaipur |
| Time to complete: | 1 day (included in previous procedure) |
| Cost to complete: | no charge |
| Comment: | |
| Procedure 6* | Notify the Municipal Corporation of about the completing of finishing work |
| Time to complete: | 33 days |
| Cost to complete: | no charge |
| Comment: | |
| Procedure 7* | Receive inspection from Municipal Corporation of Jaipur |
| Time to complete: | 1 day (included in previous procedure) |
| Cost to complete: | no charge |
| Comment: | |
| Procedure 8 | Obtain no objection certificate from fire department |
| Time to complete: | 30 days |
| Cost to complete: | INR 2000 |
| Comment: | |
| Procedure 9* | Receive inspection from fire department |
| Time to complete: | 1 day (included in previous procedure) |
| Cost to complete: | no charge |
| Comment: | |
| Procedure 10* | Apply for the use and uplift of underground water with the Rajasthan State pollution control board |
| Time to complete: | 20 days |
| Cost to complete: | INR 1000 |
| Comment: | |
| Procedure 11* | Receive inspection from Rajasthan State pollution control board |
| Time to complete: | 1 day (included in previous procedure) |
| Cost to complete: | no charge |
| Comment: | |
| Procedure 12* | Obtain no objections certificate from Public Health Department |
| Time to complete: | 15 days |
| Cost to complete: | INR 2500 |
| Comment: | |
| Procedure 13* | Apply for sanction of power connection with Rajasthan State Electricity Board |
| Time to complete: | 45 days |
| Cost to complete: | INR 75,000 (INR 50,000-100,000) |
| Comment: | |
| Procedure 14* | Receive inspection from Rajasthan State Electricity Board |
| Time to complete: | 1 day (included in previous procedure) |
| Cost to complete: | no charge |
| Comment: | |
| Procedure 15* | Obtain water and sewage connection from Jaipur Municipal Corporation |
| Time to complete: | 40 days |
| Cost to complete: | INR 5500 |
| Comment: | |
| Procedure 16* | Obtain phone connection |
| Time to complete: | 7 days |
| Cost to complete: | INR 2000 |
| Comment: | |
| Procedure 17 | Obtain completion certificate |
| Time to complete: | 45 days |
| Cost to complete: | INR 2500 |
| Comment: | |
| Procedure 18* | Receive final inspection from Municipality |
| Time to complete: | 1 day (included in previous procedure) |
| Cost to complete: | no charge |
| Comment: | |
| Procedure 19 | Obtain occupancy permit |
| Time to complete: | 25 days |
| Cost to complete: | INR 30 per square meter |
| Comment: | |
| Procedure 20* | Receive final inspection |
| Time to complete: | 1 day (included in previous procedure) |
| Cost to complete: | no charge |
| Comment: |